Production deploys are a scheduled, gated event — not a reflex. This page states the schedule the founder approved on 2026-10-22 and the gate that enforces it. The canonical texts are the rule in anuka-team-rules-stories and the gate specification in anuka-platform-design-stories; this page summarises them and links the sources.
Release windows
Section titled “Release windows”- Production deploys happen in three windows a week: Monday, Wednesday and Saturday, 10:00–14:00 ET.
- Each window has a freeze at 18:00 the day before: after the freeze, the window’s package manifest is fixed — per app: the exact commit and the stage-verification record for that commit, written in its ANUKA task.
- One production deploy per app per window. A second deploy of the same app in the same window does not happen outside the hotfix lane.
- Documentation content batches keep their own cadence (Tuesday and Friday) and are never mixed into an app release package.
The ban, and its single exception
Section titled “The ban, and its single exception”No production deploys outside the windows. The only bypass is the hotfix lane: a critical P0/P1 fix, personally approved by the founder, with the approval recorded in the ANUKA task before the deploy. A hotfix is marked in its task and counted separately in the deploy accounting. Anything else waits for the next window — including work that merely feels urgent.
The gate is a script, not a promise
Section titled “The gate is a script, not a promise”A deploy_gate check runs before promotion and verifies, for the exact package being deployed:
- the deploy is inside a window — or carries a recorded hotfix exception;
- the same commit has a recorded stage verification;
- this app has not already used its deploy in this window.
A non-zero exit means no deploy. The gate is enforced by the script, not by anyone’s word — the schedule exists precisely so that discipline does not depend on memory at 2 a.m.
Rollbacks
Section titled “Rollbacks”A rollback is the restore of an existing deploy (Netlify Publish deploy / POST /deploys/{id}/restore): it creates no new deploy and costs 0 credits. A revert pushed as a new build, or a re-uploaded bundle, is not a rollback — it is a new production deploy, charged like one and bound by the same windows and gates.
Accounting
Section titled “Accounting”A daily counter classifies every production deploy as package, hotfix, rollback or unexplained, attributed per app against the weekly cap. The Saturday retro reviews the unexplained deploys with their owners. A deploy nobody can explain is a process defect, treated like a product one.
Sources
Section titled “Sources”- The rule:
anuka-team-rules-stories— Strict ban on out-of-window production deploys (MR !14; on the steward’s review as of 2026-10-22). - The gate spec:
anuka-platform-design-stories— Deploy gate: scripted pre-promotion checks (Draft MR !132). - The audit and schedule proposal: Cost Balancer lane,
DEPLOY-SCHEDULE-PROPOSAL-2026-10-22.md(the Wednesday before adoption burned 27 production deploys — the iteration-in-production pattern this schedule ends).
Status note: this page states the founder-approved schedule in force from 2026-10-22; the rule and spec links above are updated as their merge requests land.